Vulcan Hill Hospital deliveries, construction of three builders across the seven major problems facing the construction project

War "plague" started
Jianzhong three innings not evade, do not back down, do not fear
to bear in mind the mission, the first charge, to tackle tough
just a few days to complete the
33,900 square meters high standard hospital delivery
played a nice battle and epidemic prevention
for the fight win epidemic prevention and control warfare contributed
majestic three innings forces
Feb. 2 morning, Wuhan Vulcan Hill hospital held the delivery ceremony, mayor of Wuhan, Zhou Xianwang and joint logistical support troops Baizhong Bin, deputy commander of the signing of swaps in the Vulcan Hill hospital in Wuhan file transfer, marking the Vulcan Hill hospital officially delivered to the people's army medical workers. Construction Group party secretary, chairman Zhou Naixiang, built in the third Wuhan anti-pneumonia emergency construction work group leader, built in the third party secretary, Chen Yuan, chairman of participating in the project handover ceremony.
Now, please take a look at what small series with the "stumbling block" process has, of three people is how to create a miracle in the fight with the epidemic.
01, the initial harsh conditions
before full construction, the construction site to be leveled things up to a maximum height of nearly 10 meters above the ground, existing buildings need to be removed, there is a lot of work and dredging ponds backfill task. However, the entire project built near the water, surrounding only one main road leading to the site, huge supplies of traffic in and out of pressure, gas, high pressure Qiangai large amount of coordination.
January 24 morning, built in the third set up in Wuhan anti-pneumonia emergency construction work leading group, officially formed the command center. On that day, the project admission digging machine 95 sets, 33 sets of bulldozers, rollers 5, dump truck 160, 160 managers and 240 workers gathered completed and 2,000 people since the formation of the reserve forces. On New Year's Eve, the project site machinery roar, voices, a seat small mountain of soil is leveled overnight.
02, personnel mobilization difficult
construction site, the project is almost more than 4000 workers and nearly one thousand kinds of large-scale machinery and equipment and transport vehicles a day, 24-hour work shifts, a time when the Chinese New Year holiday, many migrant workers have returned home New Year, short how much time to mobilize workers?
Approach January 23 evening, built in the third rapid mobilization of Wuhan City is overtime five construction projects of more than 1,400 workers, and other site preparation work before they can rapidly. At the same time, construction of three also GF "battle", the workers quickly called by labor subcontracting companies. Zhang, general manager of Hubei with labor service companies Fujian Ping said, the evening of January 23 after receiving the notice, on the 24th early in the morning took a bus straight to Enshi, along the road to Yichang, Jingmen, Jingzhou, Xiantao and other places to pick up workers; the same time, Wuhan surrounding rural areas to mobilize workers to come together.
03, materials demand huge
site supplies huge demand (box board room demand will reach 1650, all kinds of doors Tang of 1500, up 1.4 Articles of concrete demands, HDPE film demand will reach 100,000 square meters), temporarily during the Spring Festival stocking model will appear uneven.
Construction of three co-stick system, deployed emergency medical technicians with extensive experience in building, directly sent to Wuhan City Fire Assurance Center, the CDC and all participation units throughout the collaborative design institute design drawings. Material procurement team prior to a first time to be able to purchase the materials and equipment to institute timely feedback, targeted material showing a conventional apparatus. Enter the construction site, although the manufacturers of the board of standard models there are differences, but the construction of three of the containers "precise positioning" of the deepening of the design, the different manufacturers of materials science effective assembled together.
04, organization and coordination is difficult
in the construction of three led by the United municipal Wuhan and many other units involved in various professional and subcontractors is to reach hundreds, entire Vulcan mountain construction site, time, heavy task, limited persons and goods, number of participating units, how to work together to play the effect of 1 + 1> 2?
Efficient joint combat units is a top priority. Construction of three rapidly build organizational system, the scene was set up in Wuhan Urban Construction Bureau, built in the third, participating in the construction subcontractors three combat command system, all units build consensus, unified, complement each other, work together. All units seamlessly, supporting municipal units a day, power lines, gas pipelines in just one day on a whim move is completed, to provide protection for the duration of efficient propulsion. In the 70,000 square meters of construction site management staff from 160 people to nearly 1,000 service workers from 240 people to 4200 people, large machinery and equipment, vehicles from 300 to nearly a thousand units, field operations to implement a double shift, construction uninterrupted for 24 hours.
05, security and epidemic prevention difficult
nearly a thousand managers, more than 4,000 workers, 24 hours non-stop crashing. However, the disease still here, epidemic prevention and how to protect themselves?
All units three innings were the scene epidemic prevention and control as a top priority. Security management team set up epidemic prevention, and on-site security team is divided into two construction sync "two shifts", 24-hour security monitoring. Project established the "5 + 3 + 8" mode to carry out prevention work, "5" that is in the office area, workers living area is set at 5 fixed infrared thermometer, "3" that is, the flow temperature set point at the construction site at the 3 "8" that eight executives carry thermometer temperature measurement spot inspections to ensure that all workers at least four times a day to monitor body temperature. Vulcan Mountain project start date, not any construction site accidents, personnel participating in the construction status of the epidemic did not occur with infection.
06, infection prevention and control difficult
Vulcan Hill Hospital will focus on patients admitted to reduce the spread of the epidemic, while in the hospital, and how to protect health care workers, to prevent cross-infection?
Hospital to "clean sewage diversion, the doctor-patient diversion, diversion character" principle, adopt a strict "three districts, two-channel" design, according to medical staff "clean area - semi-polluted - polluted area" workflow layout work area. Each enters a region, completely separated from the patient care passage channel. In the isolation ward ward equipped with a transfer chamber consisting of two layers of glass and a UV systems, the patient's meals and drugs are transferred from the transfer chamber in, an ultraviolet disinfection system by passing cabin, to avoid infection. Each ward has placed two beds, a separate toilet room, under multiple protection, safe and reliable working environment for health care workers.
07, pollution control requires high
as the country's leading hospital respiratory infections, and built in such a short period of time, and proximity to the lake bosom friend, how to avoid pollution of the environment during construction, then built can meet environmental standards?
During construction, built in the third with a "two Bs one film" Construction pollution problems to solve, hospital laying 50,000 square meters of high-performance impermeable membrane, so that sewage and waste can not penetrate it. Hospital network implemented fully enclosed operation, the erection of rainwater and sewage treatment systems, after two chlorine disinfection process, after the standard before discharged into the municipal pipe network, to ensure that no contamination of the surrounding environment and surrounding lakes. Each individual wards are respectively provided is not circulated air system and exhaust system, which together form a negative pressure system to keep wards clean fresh air, after disinfection before the exhaust gas into the air; No. 1 in the south side of the ward garbage incinerators, solid waste burned focus to ensure that does not cause environmental pollution.
Battle will eventually end, victory will come
the smoke cleared
that day and night prodigiously hard battle
written in one and a
moving, inspiring and glorious deeds
will certainly timeless
guide us not forget the beginning of the heart, before continuing line

(source: construction of three)